Monday, November 22, 2010

Friday, November 19, 2010

PIPE RACK FOUNDATIONS - INSIDE PLANT


EXCAVATION WORKS ARE IN PROGRESS FOR PIPE RACK FOUNDATIONS - IN SIDE THE PLANT

PIPE RACK FOUNDATIONS

EXCAVATION WORKS ARE IN PROGRESS FOR PIPE RACK FOUNDATIONS





AUXILIARY BUILDING

REBAR AND FORM WORKS ARE IN PROGRESS FOR THE FOUNDATIONS IN AUXILIARY BUILDING

CONTROL BUILDING

FOUNDATION CONCRETING COMPLETED AND REBAR AND STAGING WORKS ARE IN PROGRESS FOR THE TIE BEAMS AND COLUMNS

AHEC CAMP PHASE-1

PORTACABINS INSTALLATION COMPLETED FOR PHASE-1 IN AHEC CAMP

FENCING FOR SPORTS COURTS - PDO/GS CAMP

GRAVEL SPREADING WORKS COMPLETED IN PDO/GS CAMP

Saturday, October 30, 2010

PIPE RACK FOUNDATIONS


EXCAVATION WORKS ARE IN PROGRESS FOR PIPE RACK FOUNDATIONS

132KV AUXILIARY BUILDING


EXCAVATION FOR FOUNDATIONS COMPLETED IN AUXILIARY BUILDING

CONTROL BUILDING


CONTROL BUILDING-EXCAVATION FOR FOUNDATIONS COMPLETED
FORM WORKS ARE IN PROGRESS FOR BLINDING

MAIN PLOT - CIVIL & BUILDING WORKS


MAIN PLOT BACKFILLING WORKS COMPLETED

BATCHING PLANT - AREA



BATCHING PLANT -FOUNDATIONS ARE READY

SEWAGE TREATMENT PLANT -400 CUM/DAY CAPACITY



STP INSTALLATION COMPLETED

RO PLANT - 500CUM/DAY CAPACITY




RO PLANT COMMISSIOING COMPLETED

AHEC CAMP - MOSQUE


MOSQUE INSTALLATION COMPLETED @ AHEC CAMP

AHEC CAMP -PHASE-1


AHEC Camp - Portacabin Installation for Phase-1 Completed

AHEC CAMP



AHEC CAMP (PHASE-1)

SUBCONTRACTOR'S (AHEC) CAMP


SUBCONTRACTOR'S (AHEC) CAMP

Ware House






WARE HOUSE ERECTION COMPLETED