Saih Nihayda Depletion Compression Project : Civil & Building Works and 132KV OHL Works
Saturday, October 30, 2010
PIPE RACK FOUNDATIONS
EXCAVATION WORKS ARE IN PROGRESS FOR PIPE RACK FOUNDATIONS
132KV AUXILIARY BUILDING
EXCAVATION FOR FOUNDATIONS COMPLETED IN AUXILIARY BUILDING
CONTROL BUILDING
CONTROL BUILDING-EXCAVATION FOR FOUNDATIONS COMPLETED
FORM WORKS ARE IN PROGRESS FOR BLINDING
MAIN PLOT - CIVIL & BUILDING WORKS
MAIN PLOT BACKFILLING WORKS COMPLETED
BATCHING PLANT - AREA
BATCHING PLANT -FOUNDATIONS ARE READY
SEWAGE TREATMENT PLANT -400 CUM/DAY CAPACITY
STP INSTALLATION COMPLETED
RO PLANT - 500CUM/DAY CAPACITY
RO PLANT COMMISSIOING COMPLETED
AHEC CAMP - MOSQUE
MOSQUE INSTALLATION COMPLETED @ AHEC CAMP
AHEC CAMP -PHASE-1
AHEC Camp - Portacabin Installation for Phase-1 Completed
AHEC CAMP
AHEC CAMP (PHASE-1)
SUBCONTRACTOR'S (AHEC) CAMP
SUBCONTRACTOR'S (AHEC) CAMP
Ware House
WARE HOUSE ERECTION COMPLETED
Friday, October 22, 2010
CAR PARKING SHELTER @ PDO/GS OFFICE AREA - COMPLETED
GS Office - Completed
PDO/GS OFFICE
PDO/GS OFFICES - COMPLETED
PDO Recreation Room
PDO RECREATION BUILDING
Friday, October 15, 2010
PDO DINING HALL
PDO/GS CAMP ENERGIZATION COMPLETED
PDO/GS CAMP ENERGISATION COMPLETED
PDO/GS CAMP
PDO/GS Camp Energization Completed
PDO/GS CAMP
Interlocking Tile Works Completed in PDO/GS Camp Area
PDO/GS Camp
PDO/GS Camp Installation Completed and the camp was occupied by PDO/GS on 01-October-2010.