Saturday, October 30, 2010

PIPE RACK FOUNDATIONS


EXCAVATION WORKS ARE IN PROGRESS FOR PIPE RACK FOUNDATIONS

132KV AUXILIARY BUILDING


EXCAVATION FOR FOUNDATIONS COMPLETED IN AUXILIARY BUILDING

CONTROL BUILDING


CONTROL BUILDING-EXCAVATION FOR FOUNDATIONS COMPLETED
FORM WORKS ARE IN PROGRESS FOR BLINDING

MAIN PLOT - CIVIL & BUILDING WORKS


MAIN PLOT BACKFILLING WORKS COMPLETED

BATCHING PLANT - AREA



BATCHING PLANT -FOUNDATIONS ARE READY

SEWAGE TREATMENT PLANT -400 CUM/DAY CAPACITY



STP INSTALLATION COMPLETED

RO PLANT - 500CUM/DAY CAPACITY




RO PLANT COMMISSIOING COMPLETED

AHEC CAMP - MOSQUE


MOSQUE INSTALLATION COMPLETED @ AHEC CAMP

AHEC CAMP -PHASE-1


AHEC Camp - Portacabin Installation for Phase-1 Completed

AHEC CAMP



AHEC CAMP (PHASE-1)

SUBCONTRACTOR'S (AHEC) CAMP


SUBCONTRACTOR'S (AHEC) CAMP

Ware House






WARE HOUSE ERECTION COMPLETED